Progress So Far…

Over the next couple of weeks we aim to go into more detail of the design efforts, fluid dynamics and mechanical analysis and the manufacturing progress, we’ll also introduce you to the team and learn about their inputs. For now though a quick update to project progress.

So as of 26th of February we have completed detailed designs of the Mk4 handbike, and started manufacture of the frame and drive train components.

1511010

Alongside this computational fluid dynamics (CFD) analysis has started, this has been undertaken by a group of Stage 5 MEng Mechanical Engineers.
CFD Work UnderwayKeep posted for more info!

Advertisements

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s